Cabinet Approves 68 Measures to accelerate the deployment of charging infrastructure
Volker Wissing: „We need to make progress on charging infrastructure“
Federal Minister Dr. Volker Wissing today in Berlin presented the bill passed by the Cabinet Charging Infrastructure Master Plan II presented. Under the leadership of the Federal Ministry of Transport, approximately 80 stakeholders—including federal states, municipalities, associations, and companies—contributed to the development of the nearly 70 measures.
Dr. Volker Wissing, Federal Minister for Digital Affairs and Transport:
How we will get around in the future is one of the most pressing issues of our time. And the world is looking to Germany on this matter. That is why we must now lead by example and continue to make our infrastructure ready for climate-friendly mobility. The Charging Infrastructure Master Plan II lays the foundation for a comprehensive, demand-driven, and user-friendly charging infrastructure for passenger cars and trucks. Our goal: to accelerate the expansion of charging infrastructure, simplify the charging process, and thereby make the transition easier for people.
Dr. Robert Habeck, Federal Minister for Economic Affairs and Climate Action:
The charging infrastructure must be integrated into the power grid in a way that supports the system. With the Charging Infrastructure Master Plan, we are setting the right course for this. An interministerial steering group will coordinate further work to ensure that the measures presented are now implemented swiftly and consistently.
Johannes Pallasch, spokesperson for the National Coordination Center for Charging Infrastructure:
Speeding up permitting processes, integrating the charging infrastructure into the power grid, and digitizing the entire system are just a few of the challenges that need to be addressed. The Charging Infrastructure Master Plan II sets out the roadmap for this. As the National Charging Infrastructure Coordination Center, we support the implementation of these measures through our demand forecasting and digital tools, among other things.
An overview of the key areas of focus in the Charging Infrastructure II Master Plan:
Integrating Charging Infrastructure and the Power System: With the help of demand planning by the National Charging Infrastructure Coordination Center, the expansion of charging infrastructure and the power grid is to be coordinated in an optimal and forward-looking manner. In collaboration with the Federal Network Agency and the grid and charging infrastructure operators, the processes for grid connection are being organized in a simpler, more transparent, and more efficient manner. In addition to streamlining processes, the primary goal is to prepare the grids for growing demands.
Improving Charging Infrastructure Through Digitalization: The Charging Infrastructure Master Plan II also serves as a digitalization strategy. As a result, data—such as the occupancy status of charging stations—will be made available in real time in the future. It will also ensure that the planning of the charging infrastructure expansion is based on solid data and analyses of the distribution and usage of charging points. To this end, private, non-public charging points will be surveyed and included for the first time.
Empowering and more fully involving local governments as key actors: Local governments have the necessary knowledge of local conditions. The master plan includes a comprehensive support package for municipalities to help them plan, implement, and finance charging infrastructure. This includes, among other things, local master plans, regional charging infrastructure managers, digital advisory and training tools, as well as guidelines and templates for optimizing planning and permitting processes.
Initiate a charging infrastructure for electric trucks: Battery-electric trucks are expected to be used more extensively for both regional and long-haul transport. To this end, a suitable charging infrastructure must be established in the near future. In 2023, the BMDV will issue a call for proposals for an initial public truck charging network. Through its own set of measures, the master plan addresses further challenges related to the construction and operation of charging infrastructure for electric trucks, such as on private company premises or when supplying electricity to non-company vehicles.
Simplifying and accelerating the development of charging infrastructure: It will become easier for companies to set up charging infrastructure. To this end, the federal government, in cooperation with local authorities, will remove obstacles in planning and permitting processes and amend legal frameworks—such as those governing building codes and environmental protection laws.
Here You can find Master Plan II as a PDF.