BMDV provides information on the tender for truck fast-charging infrastructure
The Federal Ministry for Digital and Transport Affairs (BMDV) today held an online information event on the tendering process to provide details on the planned tender for a nationwide truck fast-charging network at around 130 unmanaged rest areas as part of the market consultation.
Dr. Volker Wissing, Federal Minister for Digital Affairs and Transport: „Germany is becoming a pioneer for forward-looking charging infrastructure policy. With our tender, we are initially creating new charging facilities for trucks at around 130 locations at unmanaged service areas across the country. Together with the planned locations at managed service areas, we will cover around two thirds of the expected charging requirements for heavy goods vehicles on our freeways with 350 locations. The remaining third will then be developed privately. The first companies have already announced that they will invest in the truck charging network on private sites. I very much welcome their commitment. In September, we will start the tendering process for 5 lots, each with around 25 locations on unmanaged rest areas. From today, potential bidders as well as companies as future users will have the opportunity to comment on the tender details presented. Because only together can we succeed in creating the necessary infrastructure for climate-friendly logistics and delivery traffic.“
Johannes Pallasch, spokesman for the National Charging Infrastructure Control Center and division manager at NOW GmbH: „We are facing a historic task: over the next few years, we need to get the electrification of heavy goods vehicles on the road. In doing so, we have our sights set on this truck fast-charging network as an overall system. In the future, around 70% of public truck charging will take place at managed and unmanaged rest areas. For the industrial and logistics sector as well as for us, it is now a matter of scaling up quickly. Attractive prices and a fair competitive landscape are key to ensuring the successful ramp-up of the overall system.“
To the locations & number of charging stations:
A total of around 350 locations are being built along the freeways, of which around 220 are at managed service areas and around 130 at unmanaged service areas. The selection of the specific locations for the truck fast-charging network was carried out in six stages by the National Charging Infrastructure Control Center:
1. determination of charging requirements in long-distance transport (journeys longer than 300 km) for the year 2030.
2. localization of charging demand on sections of federal highways based on traffic and toll data.
3. selection of suitable rest areas on highways.
4. aggregation of the charging requirements per section of the federal highway at selected locations.
5. size of charging locations based on parking stays and durations.
6. determination of the number of charging points per service area, taking into account the scarcity of space and determination of the proportion of parking spaces to be converted into charging points.
To the invitation to tender:
The contract will be awarded in lots, with the planning, construction and operation of the charging infrastructure being tendered together for each lot. The contract is expected to run for eight years; the federal government is also planning an extension option for a further four years.
The approximately 130 unmanaged rest areas will be divided into five lots in order to achieve an even distribution. Each lot comprises around 25 locations. This division ensures that competition is made possible and that synergies can be exploited in the construction and operation of the charging infrastructure.
As the owner of the sites, the federal government's Autobahn GmbH is responsible for the tender and the award procedure. It will provide the required areas at freeway service areas and order the necessary grid connections from the local distribution network operators. The BMDV will provide the funding to establish these grid connections.